Hot Gas GeneratorDesign–build (D–B) is a project delivery method utilized to deliver a project in which the design | architecture | engineering and construction services are contracted by a single entity known as the design–builder or design–build contractor.  In contrast to the continuum of design – bid – build, design–build relies on a single point of responsibility contract and is used to minimize risks for the project owner and to reduce the delivery schedule by overlapping the design phase and construction phase of a project.

Located in Auburn Hills, MI — BorgWarner is a tier 1 supplier to the automotive industry.  At it’s Technical Powertrain Center, BW sought to re-task a diesel dynamometer test cell for use in advanced turbocharger design testing.  Based upon a solid existing relationship as well as previous experience in test cell construction, FM+C was awarded the project as a design-builder responsible for all engineering disciplines, architecture and construction.